iWorkshop bays, electrical and test bay by week. Drag a bar to move it, drag its end to stretch it. Red bars start before their parts arrive.
3 builds start before their parts land
AQ-2615 fabrication 23 Oct — PO-1183 Danfoss High Pressure Pumps due 2 Nov · AQ-2620 fabrication 26 Oct — PO-1185 Biorotor Systems due 10 Nov · AQ-2625 fabrication 29 Oct — PO-1188 DuPont Water Solutions due 8 Nov, PO-1189 Pentair Codeline due 19 Nov. Drag the red bar right, or expedite the freight on the PO.
Plants by week CompleteIn progressNot startedStarts before parts landPO due
Project / task
14 Sep
21 Sep
28 Sep
5 Oct
12 Oct
19 Oct
26 Oct
2 Nov
9 Nov
16 Nov
23 Nov
30 Nov
7 Dec
14 Dec
21 Dec
28 Dec
4 Jan
11 Jan
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
Engineering
Engineering
Bay 1
Electrical
Test bay
Site
Site
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
Engineering
Engineering
Bay 1
Electrical
Test bay
Site
Site
PO-1181
PO-1182
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
Engineering
Engineering
Bay 2
Electrical
Test bay
Site
Site
Engineering
Engineering
Bay 1
Electrical
Test bay
Site
Site
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
PO-1184
PO-1183
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
PO-1186
PO-1187
PO-1185
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
PO-1193
PO-1190
PO-1191
PO-1194
PO-1192
PO-1188
PO-1189
Engineering
Engineering
Bay 2
Electrical
Test bay
Site
Site
Engineering
Engineering
Container bay
Electrical
Test bay
Site
Site
Engineering
Engineering
Bay 1
Electrical
Test bay
Site
Site
Bay load — tasks running each week
| Bay | w/c 5 Oct | w/c 12 Oct | w/c 19 Oct | w/c 26 Oct |
|---|---|---|---|---|
| Bay 1 | 1 | — | — | — |
| Bay 2 | — | — | — | 1 |
| Container bay | 2 | 2 | 1 | 2 |
| Electrical | 2 | 3 | 2 | — |
| Test bay | 1 | 1 | 3 | 2 |