Quotation
Q-26-0313 Rev A
Aqueous Solutions Pty Ltd
54–56 Albemarle Street, Williamstown North VIC 3016
+61 3 9397 3066 · info@aqueous.com.au · ABN 80 124 137 015
Date 14 Jun 2026
Valid until 26 Jul 2026
Lead time 12 weeks
Prepared by Andrew Pike
Prepared for
Tarawa Water & Sanitation
Attn: Teburoro Kaiea
Betio, Tarawa, Kiribati
teburoro@tarawawater.com
Site
Betio, Tarawa, Kiribati
500 kL/d Desalination
Betio 500 kL/d containerised seawater RO
| Description | Amount ex GST |
|---|---|
Containerised seawater RO — 500 kL/d (40 ft) 42 × FilmTec SW30HRLE-440i 8" seawater RO element · 7 × Codeline 80E100 8" pressure vessel, 6-element, 1000 psi · 1 × Danfoss APP 21-26 high-pressure pump · 1 × Energy Recovery PX Q300 pressure exchanger · 2 × Grundfos CRN 15-17 stainless multistage pump · 2 × Multimedia filter vessel 1800 mm FRP · 60 × Filter sand 0.6–1.2 mm, 25 kg · 40 × Anthracite 1.2–2.4 mm, 25 kg · 16 × Garnet 0.3–0.6 mm, 25 kg · 1 × Cartridge housing 15-round 40" 316SS · 15 × Cartridge 40" 5 µm melt-blown · 3 × Grundfos DDA 7.5-16 smart dosing pump · 1 × CIP tank 1000 L with heater · 1 × Grundfos CR 32-2 CIP pump · 40 × Calcite remineralisation media, 25 kg · 3 × Signet 2850 conductivity sensor + 9900 transmitter · 3 × Promag W 50 mm electromagnetic flowmeter · 4 × Pressure transmitter 0–100 bar 316SS · 4 × Pressure transmitter 0–10 bar · 8 × Pressure gauge 0–100 bar 316SS glycerine · 1 × Turbidity analyser · 8 × Super duplex HP ball valve 25 NB · 3 × High-pressure check valve 25 NB super duplex · 14 × Super duplex 2507 pipe 25 NB Sch40, 6 m · 36 × Victaulic HP coupling 25 NB · 4 × Butterfly valve 100 mm, pneumatic actuated · 2 × Pipe fittings, supports & fasteners — set · 1 × CompactLogix PLC kit with I/O · 1 × PanelView 10" HMI · 1 × VSD 55 kW (ABB ACS580) · 2 × VSD 15 kW (ABB ACS580) · 1 × MCC switchboard, fabricated · 1 × 4G remote monitoring RTU + SCADA licence · 2 × Cable, trays & sundries — lot · 1 × 40 ft high-cube container, new build · 1 × Container fit-out — insulation, lining, A/C, lighting, safety shower · Process engineering & design · Drafting — 2D/3D & P&ID · HAZOP workshop & report · Workshop fabrication & assembly · Electrical, PLC & SCADA · Factory acceptance test · O&M manuals, logbook & drawings | $734,900.51 |
Export & commissioning package — Pacific Export crating, freight to port & customs docs · Sea freight — container, port to port · Travel & accommodation · Site installation & commissioning | $33,700.36 |
| Subtotal (ex GST) | $768,600.87 |
| GST — export, GST-free | $0.00 |
| Total (inc GST) | $768,600.87 |
Delivery: CIF Tarawa. Quotation valid for 45 days.
Payment terms: 30% deposit, progress claims.
Exclusions: Civil works, slabs and footings; feed and reject pipework beyond the container/skid flanges; power supply to the MCC; potable storage beyond the product tank; import duties and taxes at destination unless stated.
Designs are HAZOP-reviewed and built to the relevant Australian Standards. Plants are factory acceptance tested at Williamstown North before dispatch.